Ashland Bridge Deck Replacement, Half-Filled T Grid bridge grid deck fabricated by MCS

Ashland Bridge Deck Replacement

Ashland, New HampshireHalf-Filled T GridYear on file
Project Summary

Full deck replacement on an aging New Hampshire bridge using 15,000 sq ft of half-filled T grid deck across 152 panels, 76 northbound and 76 southbound, delivered in two phases. The job marked the first use of a new beam-punching die and the first MCS build with pans positioned below the cross bars.

Upward view of a bridge's structural steel framing and grid decking from below
Existing bridge conditions before rehabilitation
Step 01

The Challenge

The project required a full deck replacement on both sides of the Ashland Bridge, 15,000 square feet across 152 panels, split evenly northbound and southbound. The customer wanted one side completed and installed first with the second side delivered after, so fabrication had to be sequenced around a two-phase installation plan. On top of that, the deck was a half-filled T configuration MCS had never produced before, requiring a new beam-punching die and pans set below the cross bars, plus all field-installed materials the contractor needed to finish the system on site.

Interior of the MCS fabrication facility with overhead cranes and steel work stations
Grid panel fabrication in the MCS shop
Step 02

The MCS Approach

The Bridge Division sourced, processed, fabricated, and shipped the complete grid deck package: half-filled T panels along with splices, rebar, pans, and leveling bolts. Rather than treating the new configuration as an unknown, the team integrated the new punching die into production, proved out the below-cross-bar pan detail, and translated a first-time system into a controlled, repeatable manufacturing process. Fabrication was organized around the two 76-panel phases so each side of the bridge shipped in the order the contractor needed it.

Stacks of galvanized steel bridge grid deck panels staged outdoors for shipment
Finished grid panels staged for delivery
Step 03

The Outcome

The project ran without major fabrication or field issues. MCS held schedule discipline from sourcing through shipment, met the required due date, and supported the bridge reopening on time, finishing ahead of budget using roughly half of the labor hours originally allocated. Ashland now stands as proof that MCS can adopt new tooling, manufacture a first-time grid configuration, and coordinate phased delivery on a live bridge project without sacrificing quality or schedule.

Ashland Bridge Deck Replacement, Half-Filled T Grid grid deck fabricated by MCS
Related Projects

More Half-Filled T Grid work.

Discuss a Similar Project

Have a bridge or industrial grid project in mind?

Tell us what you're working on. The MCS Bridge team can review drawings, answer engineering questions, provide a quote, or help you evaluate the right grid system for your application.

Engineering review and system selection
Detailed quoting and procurement support
Fabrication planning and delivery coordination